When To Use
Use G743™ when completing a G742 design-build payment application. This document is suitable for any size project or payment method.
What It Does
G743 provides the continuation sheet for payment applications on design-build projects, documenting each line item's scheduled value, completion status, and materials stored. It pairs with G742 to provide both parties with a standardized payment process, ready for owner certification. The design-builder documents the status of the contract sum to date, including work completed and stored, retainage, previous payments, change order summary, and the current amount requested.
Additional Information
AIA does not publish a standard schedule of values form. The schedule of values is prepared per Sections 9.2 of A141 and 10.2 of A141PDB.